Current Project Activity
 

Blake to Market streets (Block 0) 
  • No current activity 
Market to Larimer streets (Block 1)
  • Phase 1 of improvements underway  

Larimer to Lawrence streets (Block 2) 

  • Phase 1 of improvements underway
    • Larimer intersection work through mid-November
      • Double-lane closures
    • Full intersection closure as soon as mid-November for approximately four weeks
      • Larimer Street will be in a temporary two-way configuration between 15th & 16th and 16th & 17th streets to allow access 
Lawrence to Arapahoe streets (Block 3) 
  • Phase 1 of improvements underway  
    • Lawrence intersection work started on Oct. 24 
      • Double-lane closures
    • Full intersection closure as soon as December 
      • Lawrence Street will be in a temporary two-way configuration between 15th & 16th and 16th & 17th streets to allow access 
Arapahoe to Curtis streets (Block 4) 
  • Phase 1 of improvements underway
  • Xcel utility work on Arapahoe Street
    • Bike lane closure on Arapahoe and partial sidewalk closure as soon as Oct. 26 for less than a week 

Curtis to California streets (Block 5-7)

  • No current activity
California to Broadway (Blocks 8-13)  
  • Preconstruction utility work on California to start in late October 
    • Single-lane closure 
    • No light rail impacts
  • Potholing work underway 
Potholing Activities 
  • The 16th Street Mall Project will continue potholing activities to confirm decades of existing data about conditions on, around, and under the Mall. 
  • By potholing, which includes drilling holes into the pavement in multiple locations, the team will be able to confirm the location of existing underground utilities. By identifying existing utilities, such as water/sewer pipes and electrical conduit lines, the team will be able to reduce the chance of unexpectedly encountering one of these lines during construction.  
  • Activities will require occasional lane and sidewalk closures on the 16th Street Mall and on cross streets between Market Street and Broadway. Signage will clearly identify how pedestrians and motorists can navigate any expected closures. 
RTD Bus Routes
The RTD Free MallRide shuttle continues to run during the 16th Street Mall Project, rerouted to 15th and 17th streets between Wazee and Welton streets. For more information on RTD's Free MallRide detours, visit rtd-denver.com/app/alerts/routes/MALL  
 
Work Hours 
  • Monday through Friday, 7 a.m. to 7 p.m.;  
  • Weekend work between 8 a.m. and 5 p.m. can also be anticipated; and 
  • Material deliveries and staging may occur overnight. 
Construction work and schedules are weather-dependent and subject to change. For updated information, visit our website at denvergov.org/16thStreetMall.
Connect with the Project Team 
 
Trailer Talks
To meet 16th Street Mall visitors where they are, project team members will staff a mobile kiosk on the Mall to provide project information and answer questions from the public. Find us at the Outer Space area at 16th and Welton streets on Thursday, Oct. 27, from noon to 1 p.m. We hope to see you there! 

 
 Clean & Safe Mobile App

Directly report non-emergency public safety and maintenance concerns occurring in the Downtown Denver area. The Clean and Safe Program covers the Business Improvement District for the 120 blocks of Downtown Denver, including LoDo, Upper Downtown, and the Convention Center corridor. 

To download the app, go to the Apple Store or Google Play store and search “Clean & Safe - Downtown Denver." 

Mobile App
Need 16th Street Mall information on the go? Download our mobile app to:
  • Access the overview map of all project activities; 
  • Learn about the project and each construction phase; 
  • Find businesses along the Mall;
  • Sign up for block-by-block notifications on construction impacts, phase changes and more to best plan your route; and 
  • Connect with the project team with concerns or questions from your mobile device.
To download the app, go to the Apple Store or Google Play store and search “16th Street Mall Project."








 






This email was sent to garyvdrn@msn.com
why did I get this?    unsubscribe from this list    update subscription preferences
CIG PR · 1660 Lincoln St Ste 1800 · Denver, CO 80264-9906 · USA